Variation Register
All variations across contracts (spec §7.14.4)
| No. | Contract | Description | Submitted | Assessed | Approved | Status | Cumulative (Approved) |
|---|---|---|---|---|---|---|---|
| VO-01 | Meedhoo Council Office Building | Variation 1: additional foundation works due to soft ground. | MVR 28,088.14 | MVR 26,683.73 | MVR 25,279.33 | Approved | MVR 25,279.33 |
| VO-02 | Meedhoo Council Office Building | Variation 2: increased blockwork to revised layout. | MVR 42,132.20 | MVR 40,025.59 | MVR 37,918.98 | Recommended | MVR 25,279.33 |
| VO-01 | Meedhoo Pre-School (3 Classrooms) | Variation 1: additional foundation works due to soft ground. | MVR 16,852.88 | MVR 16,010.24 | MVR 15,167.59 | Approved | MVR 40,446.92 |
| VO-01 | Meedhoo Waste Management Centre | Variation 1: additional foundation works due to soft ground. | MVR 15,453.72 | MVR 14,681.03 | MVR 13,908.35 | Approved | MVR 54,355.27 |
| VO-02 | Meedhoo Waste Management Centre | Variation 2: increased blockwork to revised layout. | MVR 23,180.58 | MVR 22,021.55 | MVR 20,862.52 | Recommended | MVR 54,355.27 |
| VO-03 | Meedhoo Waste Management Centre | Variation 3: additional external lighting. | MVR 30,907.44 | MVR 29,362.07 | MVR 27,816.70 | Recommended | MVR 54,355.27 |
| 1 | Meedhoo Stage Foundation | 1 | MVR 12.00 | MVR 0.00 | — | Draft | MVR 54,355.27 |