Meedhoo Pre-School (3 Classrooms)
Contract · Addu Builders Pvt Ltd
Contract Amount
MVR 1,685,288.16
Approved Variations
MVR 15,167.59
Revised Sum
MVR 1,700,455.75
Certified to Date
MVR 856,946.56
Balance
MVR 843,509.19
Contract Information
Status
Active
Retention %
5.0%
Advance %
15.0%
Contract Date
26/01/2026
Commencement
26/01/2026
Completion
26/11/2026
LD Reference
0.05% per day, capped 10%
BOQ Version
Linked
Variations
| No. | Description | Submitted | Approved | Status |
|---|---|---|---|---|
| VO-01 | Variation 1: additional foundation works due to soft ground. | MVR 16,852.88 | MVR 15,167.59 | Approved |