Meedhoo Pre-School (3 Classrooms)

Contract · Addu Builders Pvt Ltd

Contract Amount
MVR 1,685,288.16
Approved Variations
MVR 15,167.59
Revised Sum
MVR 1,700,455.75
Certified to Date
MVR 856,946.56
Balance
MVR 843,509.19

Contract Information

Status
Active
Retention %
5.0%
Advance %
15.0%
Contract Date
26/01/2026
Commencement
26/01/2026
Completion
26/11/2026
LD Reference
0.05% per day, capped 10%
BOQ Version
Linked

Variations

No.DescriptionSubmittedApprovedStatus
VO-01Variation 1: additional foundation works due to soft ground.MVR 16,852.88MVR 15,167.59Approved

Payment Certificates

No.TitleGrossNet PayableStatus
IPC #1IPC 01MVR 561,762.72MVR 450,825.82Paid
IPC #2IPC 02MVR 1,123,525.44MVR 406,120.74Approved