Variation VO-02
Meedhoo Council Office Building · Quantity increase
Recommended
Submitted
MVR 42,132.20
Assessed
MVR 40,025.59
Approved
MVR 37,918.98
Time Impact
10 days
Details
Type
Quantity increase
Initiated By
Consultant
Date
26/12/2025
Reason
Client request
Drawing Ref
—
Instruction Ref
—
Related Item
—
Description
Variation 2: increased blockwork to revised layout.
Workflow
✓
Draft✓
Submitted✓
Under Review4
Recommended5
ApprovedVariation Items
| Code | Description | Unit | Qty | Rate | Amount | |
|---|---|---|---|---|---|---|
| VO2.001 | Additional work as instructed | sum | 1.000 | MVR 37,918.98 | MVR 37,918.98 | |
| MVR 0.00 |
Submitted amount auto-syncs to the sum of item amounts (MVR 42,132.20). Negative qty/rate allowed for omissions.