Meedhoo Waste Management Centre

Contract · Addu Builders Pvt Ltd

Contract Amount
MVR 1,545,372.04
Approved Variations
MVR 13,908.35
Revised Sum
MVR 1,559,280.39
Certified to Date
MVR 961,406.85
Balance
MVR 597,873.54

Contract Information

Status
Completed
Retention %
5.0%
Advance %
15.0%
Contract Date
26/04/2025
Commencement
26/04/2025
Completion
26/04/2026
LD Reference
0.05% per day, capped 10%
BOQ Version
Linked

Variations

No.DescriptionSubmittedApprovedStatus
VO-01Variation 1: additional foundation works due to soft ground.MVR 15,453.72MVR 13,908.35Approved
VO-02Variation 2: increased blockwork to revised layout.MVR 23,180.58MVR 20,862.52Recommended
VO-03Variation 3: additional external lighting.MVR 30,907.44MVR 27,816.70Recommended

Payment Certificates

No.TitleGrossNet PayableStatus
IPC #1IPC 01MVR 309,074.41MVR 277,245.93Paid
IPC #2IPC 02MVR 618,148.82MVR 252,649.79Paid
IPC #3IPC 03MVR 927,223.22MVR 228,053.62Paid
IPC #4IPC 04MVR 1,236,297.63MVR 203,457.51Approved