Meedhoo Waste Management Centre
Contract · Addu Builders Pvt Ltd
Contract Amount
MVR 1,545,372.04
Approved Variations
MVR 13,908.35
Revised Sum
MVR 1,559,280.39
Certified to Date
MVR 961,406.85
Balance
MVR 597,873.54
Contract Information
Status
Completed
Retention %
5.0%
Advance %
15.0%
Contract Date
26/04/2025
Commencement
26/04/2025
Completion
26/04/2026
LD Reference
0.05% per day, capped 10%
BOQ Version
Linked
Variations
| No. | Description | Submitted | Approved | Status |
|---|---|---|---|---|
| VO-01 | Variation 1: additional foundation works due to soft ground. | MVR 15,453.72 | MVR 13,908.35 | Approved |
| VO-02 | Variation 2: increased blockwork to revised layout. | MVR 23,180.58 | MVR 20,862.52 | Recommended |
| VO-03 | Variation 3: additional external lighting. | MVR 30,907.44 | MVR 27,816.70 | Recommended |