Meedhoo Council Office Building

Contract · Addu Builders Pvt Ltd

Contract Amount
MVR 2,808,813.60
Approved Variations
MVR 25,279.33
Revised Sum
MVR 2,834,092.93
Certified to Date
MVR 1,635,656.42
Balance
MVR 1,198,436.51

Contract Information

Status
Active
Retention %
5.0%
Advance %
15.0%
Contract Date
26/10/2025
Commencement
26/10/2025
Completion
26/12/2026
LD Reference
0.05% per day, capped 10%
BOQ Version
Linked

Variations

No.DescriptionSubmittedApprovedStatus
VO-01Variation 1: additional foundation works due to soft ground.MVR 28,088.14MVR 25,279.33Approved
VO-02Variation 2: increased blockwork to revised layout.MVR 42,132.20MVR 37,918.98Recommended

Payment Certificates

No.TitleGrossNet PayableStatus
IPC #1IPC 01MVR 702,203.40MVR 601,100.15Paid
IPC #2IPC 02MVR 1,404,406.80MVR 545,218.80Paid
IPC #3IPC 03MVR 2,106,610.20MVR 489,337.47Paid