Variation VO-01

Meedhoo Waste Management Centre · Design change

Approved
Submitted
MVR 15,453.72
Assessed
MVR 14,681.03
Approved
MVR 13,908.35
Time Impact
5 days

Details

Type
Design change
Initiated By
Consultant
Date
26/05/2025
Reason
Site condition
Drawing Ref
Instruction Ref
Related Item
Description
Variation 1: additional foundation works due to soft ground.
Workflow
Draft
Submitted
Under Review
Recommended
5
Approved
No further transitions.
Variation Items
CodeDescriptionUnitQtyRateAmount
VO1.001Additional work as instructedsum1.000MVR 13,908.35MVR 13,908.35
MVR 0.00