Variation VO-01
Meedhoo Pre-School (3 Classrooms) · Design change
Approved
Submitted
MVR 16,852.88
Assessed
MVR 16,010.24
Approved
MVR 15,167.59
Time Impact
5 days
Details
Type
Design change
Initiated By
Consultant
Date
26/02/2026
Reason
Site condition
Drawing Ref
—
Instruction Ref
—
Related Item
—
Description
Variation 1: additional foundation works due to soft ground.
Workflow
✓
Draft✓
Submitted✓
Under Review✓
Recommended5
ApprovedNo further transitions.
Variation Items
| Code | Description | Unit | Qty | Rate | Amount | |
|---|---|---|---|---|---|---|
| VO1.001 | Additional work as instructed | sum | 1.000 | MVR 15,167.59 | MVR 15,167.59 | |
| MVR 0.00 |
Submitted amount auto-syncs to the sum of item amounts (MVR 16,852.88). Negative qty/rate allowed for omissions.