F
Fathimath QS
qs@boq.mv
Settings

Variation VO-01

Meedhoo Pre-School (3 Classrooms) · Design change

Approved
Submitted
MVR 16,852.88
Assessed
MVR 16,010.24
Approved
MVR 15,167.59
Time Impact
5 days

Details

Type
Design change
Initiated By
Consultant
Date
26/02/2026
Reason
Site condition
Drawing Ref
Instruction Ref
Related Item
Description
Variation 1: additional foundation works due to soft ground.
Workflow
Draft
Submitted
Under Review
Recommended
5
Approved
No further transitions.
Variation Items
CodeDescriptionUnitQtyRateAmount
VO1.001Additional work as instructedsum1.000MVR 15,167.59MVR 15,167.59
MVR 0.00

Submitted amount auto-syncs to the sum of item amounts (MVR 16,852.88). Negative qty/rate allowed for omissions.