Interim Payment Certificate #2
Meedhoo Waste Management Centre · IPC 02
Paid
Gross Work Done
MVR 618,148.82
Retention
MVR 32,965.88
Previous Certified
MVR 315,750.42
Net Payable
MVR 252,649.79
Period
From
26/05/2025
To
26/06/2025
Retention %
5%
Workflow
✓
Draft✓
Contractor Claim✓
QS Review✓
Consultant✓
Finance✓
Approved7
PaidNo further transitions.
Progress Entry
| Code | Description | Unit | Contract | Prev | Current | Cumulative | Rate | Current Amt | Cumul. Amt | |
|---|---|---|---|---|---|---|---|---|---|---|
| 01.001 | Mobilization, site establishment and transport of plant & materials to Meedhoo | sum | 1.000 | 0.200 | 0.200 | 0.400 | MVR 0.00 | MVR 0.00 | MVR 0.00 | |
| 01.002 | Site office, stores, sanitary facilities and temporary services for contract period | sum | 1.000 | 0.200 | 0.200 | 0.400 | MVR 0.00 | MVR 0.00 | MVR 0.00 | |
| 01.003 | Insurances, performance bond and statutory permits | sum | 1.000 | 0.200 | 0.200 | 0.400 | MVR 0.00 | MVR 0.00 | MVR 0.00 | |
| 03.001 | Excavate for foundations in all soils incl. disposal of surplus material | m³ | 64.000 | 12.800 | 12.800 | 25.600 | MVR 0.00 | MVR 0.00 | MVR 0.00 | |
| MVR 0.00 |
Gross work done auto-syncs to the sum of current amounts once items exist (MVR 618,148.82).
Certificate Summary
Gross work doneMVR 618,148.82
Additions
Variations+ MVR 13,352.02
Materials on site+ MVR 27,816.70
Gross totalMVR 659,317.54
Deductions
Previous certified− MVR 315,750.42
Retention (5%)− MVR 32,965.88
Advance recovery− MVR 57,951.45
Other deductions− MVR 0.00
Net payable (preview)MVR 252,649.79
Saved net payable: MVR 252,649.79. Click “Save summary” to persist.