Interim Payment Certificate #4
Meedhoo Waste Management Centre · IPC 04
Approved
Gross Work Done
MVR 1,236,297.63
Retention
MVR 63,613.69
Previous Certified
MVR 947,251.24
Net Payable
MVR 203,457.51
Period
From
26/07/2025
To
26/08/2025
Retention %
5%
Workflow
✓
Draft✓
Contractor Claim✓
QS Review✓
Consultant✓
Finance6
Approved7
PaidProgress Entry
| Code | Description | Unit | Contract | Prev | Current | Cumulative | Rate | Current Amt | Cumul. Amt | |
|---|---|---|---|---|---|---|---|---|---|---|
| 01.001 | Mobilization, site establishment and transport of plant & materials to Meedhoo | sum | 1.000 | 0.600 | 0.200 | 0.800 | MVR 0.00 | MVR 0.00 | MVR 0.00 | |
| 01.002 | Site office, stores, sanitary facilities and temporary services for contract period | sum | 1.000 | 0.600 | 0.200 | 0.800 | MVR 0.00 | MVR 0.00 | MVR 0.00 | |
| 01.003 | Insurances, performance bond and statutory permits | sum | 1.000 | 0.600 | 0.200 | 0.800 | MVR 0.00 | MVR 0.00 | MVR 0.00 | |
| 03.001 | Excavate for foundations in all soils incl. disposal of surplus material | m³ | 64.000 | 38.400 | 12.800 | 51.200 | MVR 0.00 | MVR 0.00 | MVR 0.00 | |
| MVR 0.00 |
Gross work done auto-syncs to the sum of current amounts once items exist (MVR 1,236,297.63).
Certificate Summary
Gross work doneMVR 1,236,297.63
Additions
Variations+ MVR 26,704.03
Materials on site+ MVR 9,272.23
Gross totalMVR 1,272,273.89
Deductions
Previous certified− MVR 947,251.24
Retention (5%)− MVR 63,613.69
Advance recovery− MVR 57,951.45
Other deductions− MVR 0.00
Net payable (preview)MVR 203,457.51
Saved net payable: MVR 203,457.51. Click “Save summary” to persist.