Interim Payment Certificate #2
Meedhoo Pre-School (3 Classrooms) · IPC 02
Approved
Gross Work Done
MVR 1,123,525.44
Retention
MVR 58,232.32
Previous Certified
MVR 573,896.80
Net Payable
MVR 406,120.74
Period
From
26/02/2026
To
26/03/2026
Retention %
5%
Workflow
✓
Draft✓
Contractor Claim✓
QS Review✓
Consultant✓
Finance6
Approved7
PaidProgress Entry
| Code | Description | Unit | Contract | Prev | Current | Cumulative | Rate | Current Amt | Cumul. Amt | |
|---|---|---|---|---|---|---|---|---|---|---|
| 01.001 | Mobilization, site establishment and transport of plant & materials to Meedhoo | sum | 1.000 | 0.330 | 0.330 | 0.670 | MVR 0.00 | MVR 0.00 | MVR 0.00 | |
| 01.002 | Site office, stores, sanitary facilities and temporary services for contract period | sum | 1.000 | 0.330 | 0.330 | 0.670 | MVR 0.00 | MVR 0.00 | MVR 0.00 | |
| 01.003 | Insurances, performance bond and statutory permits | sum | 1.000 | 0.330 | 0.330 | 0.670 | MVR 0.00 | MVR 0.00 | MVR 0.00 | |
| 03.001 | Excavate for foundations in all soils incl. disposal of surplus material | m³ | 48.000 | 16.000 | 16.000 | 32.000 | MVR 0.00 | MVR 0.00 | MVR 0.00 | |
| MVR 0.00 |
Gross work done auto-syncs to the sum of current amounts once items exist (MVR 1,123,525.44).
Certificate Summary
Gross work doneMVR 1,123,525.44
Additions
Variations+ MVR 24,268.15
Materials on site+ MVR 16,852.88
Gross totalMVR 1,164,646.47
Deductions
Previous certified− MVR 573,896.80
Retention (5%)− MVR 58,232.32
Advance recovery− MVR 126,396.61
Other deductions− MVR 0.00
Net payable (preview)MVR 406,120.74
Saved net payable: MVR 406,120.74. Click “Save summary” to persist.