Interim Payment Certificate #3
Meedhoo Council Office Building · IPC 03
Paid
Gross Work Done
MVR 2,106,610.20
Retention
MVR 108,658.95
Previous Certified
MVR 1,434,741.98
Net Payable
MVR 489,337.47
Period
From
26/12/2025
To
26/01/2026
Retention %
5%
Workflow
✓
Draft✓
Contractor Claim✓
QS Review✓
Consultant✓
Finance✓
Approved7
PaidNo further transitions.
Progress Entry
| Code | Description | Unit | Contract | Prev | Current | Cumulative | Rate | Current Amt | Cumul. Amt | |
|---|---|---|---|---|---|---|---|---|---|---|
| 01.001 | Mobilization, site establishment and transport of plant & materials to Meedhoo | sum | 1.000 | 0.500 | 0.250 | 0.750 | MVR 0.00 | MVR 0.00 | MVR 0.00 | |
| 01.002 | Site office, stores, sanitary facilities and temporary services for contract period | sum | 1.000 | 0.500 | 0.250 | 0.750 | MVR 0.00 | MVR 0.00 | MVR 0.00 | |
| 01.003 | Insurances, performance bond and statutory permits | sum | 1.000 | 0.500 | 0.250 | 0.750 | MVR 0.00 | MVR 0.00 | MVR 0.00 | |
| 03.001 | Excavate for foundations in all soils incl. disposal of surplus material | m³ | 80.000 | 40.000 | 20.000 | 60.000 | MVR 0.00 | MVR 0.00 | MVR 0.00 | |
| MVR 0.00 |
Gross work done auto-syncs to the sum of current amounts once items exist (MVR 2,106,610.20).
Certificate Summary
Gross work doneMVR 2,106,610.20
Additions
Variations+ MVR 45,502.78
Materials on site+ MVR 21,066.10
Gross totalMVR 2,173,179.08
Deductions
Previous certified− MVR 1,434,741.98
Retention (5%)− MVR 108,658.95
Advance recovery− MVR 140,440.68
Other deductions− MVR 0.00
Net payable (preview)MVR 489,337.47
Saved net payable: MVR 489,337.47. Click “Save summary” to persist.