Meedhoo Friday Mosque Renovation — Construction Tender

ADM-2026-004/T01 · Meedhoo Friday Mosque Renovation

BOQ Items
16
Engineer Estimate
MVR 1,677,564.00
Registered Bidders
4
Addenda
1

Package Information

Tender No.
ADM-2026-004/T01
Client
Ministry of Islamic Affairs
Status
Published
BOQ Version
Tender BOQ v1 (v1)
Submission Deadline
26/07/2026
Clarification Deadline
26/06/2026
Description
Open tender for the construction of Meedhoo Friday Mosque Renovation.
Instructions to Bidders
Bids in MVR, inclusive of all island logistics. Validity 90 days.

Tender BOQ Items

CodeDescriptionUnitQty
01.001Mobilization, site establishment and transport of plant & materials to Meedhoosum1.000
01.002Site office, stores, sanitary facilities and temporary services for contract periodsum1.000
01.003Insurances, performance bond and statutory permitssum1.000
03.001Excavate for foundations in all soils incl. disposal of surplus material56.000
03.002Hardcore filling to make up levels, compacted in layers31.500
04.001Grade C25 reinforced concrete to foundations and ground beams28.000
04.002Grade C30 reinforced concrete to suspended slabs and columns45.500
05.001High-yield steel reinforcement, cut, bend and fix to detailkg6,440.000
06.001Sawn formwork to sides and soffits of beams, columns and slabs434.000
07.001200mm hollow concrete block walls in cement mortar 1:4490.000
13.00113mm cement & sand plaster to internal block walls, steel-trowel finish910.000
14.001Supply and lay 600x600 ceramic floor tiles on cement bedding350.000
15.001Suspended gypsum board ceiling on metal grid, incl. access panels294.000
16.001Prepare and apply primer + two coats emulsion to internal walls/ceilings1,190.000
10.001Aluminium-framed glazed windows with mosquito mesh, complete59.500
10.002Solid-core timber flush doors with ironmongery, hung and fixednr12.600

Tender BOQ Review (AI)

  • ImportantTile works included but adhesive/grout missing.
  • ImportantPlumbing fixtures included but testing & commissioning missing.
  • ImportantPreliminaries section appears missing.
  • SuggestedTesting & commissioning may be missing.

Addenda

#TitleNotesDate
1Clarification of MEP scopeMEP commissioning included in respective provisional sums.26/06/2026

Registered Bidders

CompanyContactBid ItemsTotalStatus
Addu Builders Pvt LtdTender Desk16MVR 1,423,894.51Submitted
Equator ConstructionTender Desk16MVR 1,534,588.45Submitted
Reef Engineering Pvt LtdTender Desk16MVR 1,645,366.85Submitted
Southern ContractorsTender Desk16MVR 1,756,086.15Submitted