Meedhoo Link Road & Drainage
ADM-2026-006 · Road Development Corporation · Meedhoo
Detailed EstimateEdit
TypeRoad and pavement
LocationMeedhoo, Addu City
ContractLump sum
CurrencyMVR
QSFathimath QS
Completion—
Estimated Cost
MVR 3,833,087.50
Subtotal MVR 3,066,470.00
GST
MVR 306,647.00
@ 8% · exclusive
Grand Total
MVR 4,139,734.50
Pending Approvals
0
8 items
Cost by Section
Tap to drill downBOQ Versions
Open BOQ Editor →| Version | Type | Items | Status | Updated |
|---|---|---|---|---|
| v1 · Detailed Estimate v1 | Internal estimate | 8 | Draft | 26/06/2026 |
Cost Trend (across versions)
v1 Detailed Estimate v13,066,470
Cost Build-up
- Subtotal
- MVR 3,066,470.00
- Overhead (10%)
- MVR 306,647.00
- Profit (10%)
- MVR 306,647.00
- Contingency (5%)
- MVR 153,323.50
- Estimated cost
- MVR 3,833,087.50
- GST @ 8%
- MVR 306,647.00
- Grand total
- MVR 4,139,734.50
Material / Labour / Equipment
Material2,107,270
Labour224,400
Equipment0
Other734,800
Latest BOQ Version
Quick Links
Details
- Type
- Road and pavement
- Contract
- Lump sum
- Procurement
- Open tender
- Remoteness
- Remote inhabited island
- PM
- Ahmed Admin
- QS
- Fathimath QS
- Consultant
- Addu Consult Pvt Ltd
- Start
- —
- Completion
- —