F
Fathimath QS
qs@boq.mv
Settings

Meedhoo Link Road & Drainage

ADM-2026-006 · Road Development Corporation · Meedhoo

Detailed EstimateEdit
TypeRoad and pavement
LocationMeedhoo, Addu City
ContractLump sum
CurrencyMVR
QSFathimath QS
Completion
Estimated Cost
MVR 3,833,087.50
Subtotal MVR 3,066,470.00
GST
MVR 306,647.00
@ 8% · exclusive
Grand Total
MVR 4,139,734.50
Pending Approvals
0
8 items

Cost by Section

Tap to drill down
VersionTypeItemsStatusUpdated
v1 · Detailed Estimate v1Internal estimate8Draft26/06/2026

Cost Trend (across versions)

v1 Detailed Estimate v13,066,470

Cost Build-up

Subtotal
MVR 3,066,470.00
Overhead (10%)
MVR 306,647.00
Profit (10%)
MVR 306,647.00
Contingency (5%)
MVR 153,323.50
Estimated cost
MVR 3,833,087.50
GST @ 8%
MVR 306,647.00
Grand total
MVR 4,139,734.50

Material / Labour / Equipment

Material2,107,270
Labour224,400
Equipment0
Other734,800

Latest BOQ Version

Details

Type
Road and pavement
Contract
Lump sum
Procurement
Open tender
Remoteness
Remote inhabited island
PM
Ahmed Admin
QS
Fathimath QS
Consultant
Addu Consult Pvt Ltd
Start
Completion