F
Fathimath QS
qs@boq.mv
Settings

Bid Comparison

Meedhoo Council Office Building — Construction Tender · ADM-2026-001/T01

Engineer Estimate
MVR 3,065,200.00
Addu Builders Pvt Ltd
#1
MVR 2,808,813.60
-8.4% vs estimate
Equator Construction
#2
MVR 3,027,199.91
-1.2% vs estimate
Reef Engineering Pvt Ltd
#3
MVR 3,245,709.67
+5.9% vs estimate
Legend Lowest rate Abnormally low Abnormally high Missing rateRecommended low bidder: Addu Builders Pvt Ltd
CodeDescriptionUnitQtyEngr. Rate
Addu Builders Pvt Ltd#1
Equator Construction#2
Reef Engineering Pvt Ltd#3
Southern Contractors#4
01.001Mobilization, site establishment and transport of plant & materials to Meedhoosum1.000165,000.00149,985.00161,650.50173,316.00184,981.50
01.002Site office, stores, sanitary facilities and temporary services for contract periodsum1.00078,000.0070,902.0076,416.6081,931.2087,445.80
01.003Insurances, performance bond and statutory permitssum1.00045,000.0040,905.0044,086.5047,268.0050,449.50
03.001Excavate for foundations in all soils incl. disposal of surplus material80.000320.00290.88313.50336.13358.75
03.002Hardcore filling to make up levels, compacted in layers45.000480.00436.32470.26504.19538.13
04.001Grade C25 reinforced concrete to foundations and ground beams40.0002,850.002,590.652,792.152,993.643,195.14
04.002Grade C30 reinforced concrete to suspended slabs and columns65.0003,050.002,772.452,988.093,203.723,419.36
05.001High-yield steel reinforcement, cut, bend and fix to detailkg9,200.00021.0019.0920.5722.0623.54
06.001Sawn formwork to sides and soffits of beams, columns and slabs620.000285.00259.07279.21299.36319.51
07.001200mm hollow concrete block walls in cement mortar 1:4700.000365.00331.79357.59383.40409.20
13.00113mm cement & sand plaster to internal block walls, steel-trowel finish1,300.000135.00125.15134.88144.61154.35
14.001Supply and lay 600x600 ceramic floor tiles on cement bedding500.000425.00393.98424.62455.26485.90
15.001Suspended gypsum board ceiling on metal grid, incl. access panels420.000390.00361.53389.65417.77445.89
16.001Prepare and apply primer + two coats emulsion to internal walls/ceilings1,700.00095.0088.0794.91101.76108.61
10.001Aluminium-framed glazed windows with mosquito mesh, complete85.0001,850.001,714.951,848.341,981.722,115.11
10.002Solid-core timber flush doors with ironmongery, hung and fixednr18.0004,200.003,893.404,196.224,499.044,801.86
17.001Plumbing & sanitary installation complete with fixtures, testing & commissioningsum1.000245,000.00227,115.00244,779.50262,444.00280,108.50
18.001Electrical wiring, distribution boards, fittings & accessories completesum1.000320,000.00296,640.00319,712.00342,784.00365,856.00
09.0010.5mm colour-coated roofing sheets on steel purlins incl. flashings360.000540.00490.86529.04567.22605.39
21.001Interlocking paving blocks to external areas on sand bedding280.000310.00265.05285.66306.28326.90
Bid TotalMVR 3,065,200.00MVR 2,808,813.60MVR 3,027,199.91MVR 3,245,709.67MVR 3,464,131.38
Variance vs engineer estimate-8.4%-1.2%+5.9%+13.0%
Rank / missing rates#1#2#3#4

Bid Import

Download the bid template, have the bidder fill the Rate column, and upload the returned file — or paste line rates as itemCode,rate. Either way, rates are matched to this tender's BOQ item codes and amounts compute from BOQ quantities.

Bidders fill the Rate column of the downloaded template and return it. Rows are matched to the tender BOQ by Item No.

How it works
  1. Click ↓ Bid template to download the unpriced BOQ.
  2. Send it to the bidder; they fill the Rate column only.
  3. Pick the bidder, choose their returned file, and import.
  4. Amounts use BOQ quantities; rates are flagged vs the engineer estimate. A re-import replaces the prior file.