Meedhoo Waste Management Centre
ADM-2026-010 · WAMCO · Meedhoo
Final AccountEdit
TypeUtility works
LocationMeedhoo, Addu City
ContractLump sum
CurrencyMVR
QSFathimath QS
Completion26/04/2026
Estimated Cost
MVR 2,119,050.00
Subtotal MVR 1,695,240.00
GST
MVR 169,524.00
@ 8% · exclusive
Grand Total
MVR 2,288,574.00
Pending Approvals
0
14 items
Cost by Section
Tap to drill downBOQ Versions
Open BOQ Editor →| Version | Type | Items | Status | Updated |
|---|---|---|---|---|
| v1 · Final Account v1 | Contract BOQ | 14 | Approved | 26/06/2026 |
Cost Trend (across versions)
v1 Final Account v11,695,240
Cost Build-up
- Subtotal
- MVR 1,695,240.00
- Overhead (10%)
- MVR 169,524.00
- Profit (10%)
- MVR 169,524.00
- Contingency (5%)
- MVR 84,762.00
- Estimated cost
- MVR 2,119,050.00
- GST @ 8%
- MVR 169,524.00
- Grand total
- MVR 2,288,574.00
Material / Labour / Equipment
Material992,360
Labour20,480
Equipment0
Other682,400
Latest BOQ Version
v1 · Final Account v1
Approved
Quick Links
Details
- Type
- Utility works
- Contract
- Lump sum
- Procurement
- Open tender
- Remoteness
- Remote inhabited island
- PM
- Ahmed Admin
- QS
- Fathimath QS
- Consultant
- Addu Consult Pvt Ltd
- Start
- 26/04/2025
- Completion
- 26/04/2026