Meedhoo Staff Quarters (8 Units)
ADM-2026-007 · Addu City Council · Meedhoo
Detailed EstimateEdit
TypeResidential building
LocationMeedhoo, Addu City
ContractLump sum
CurrencyMVR
QSFathimath QS
Completion—
Estimated Cost
MVR 4,597,800.00
Subtotal MVR 3,678,240.00
GST
MVR 367,824.00
@ 8% · exclusive
Grand Total
MVR 4,965,624.00
Pending Approvals
0
20 items
Cost by Section
Tap to drill downBOQ Versions
Open BOQ Editor →| Version | Type | Items | Status | Updated |
|---|---|---|---|---|
| v1 · Detailed Estimate v1 | Internal estimate | 20 | Draft | 26/06/2026 |
Cost Trend (across versions)
v1 Detailed Estimate v13,678,240
Cost Build-up
- Subtotal
- MVR 3,678,240.00
- Overhead (10%)
- MVR 367,824.00
- Profit (10%)
- MVR 367,824.00
- Contingency (5%)
- MVR 183,912.00
- Estimated cost
- MVR 4,597,800.00
- GST @ 8%
- MVR 367,824.00
- Grand total
- MVR 4,965,624.00
Material / Labour / Equipment
Material2,623,920
Labour30,720
Equipment0
Other1,023,600
Latest BOQ Version
Quick Links
Details
- Type
- Residential building
- Contract
- Lump sum
- Procurement
- Open tender
- Remoteness
- Remote inhabited island
- PM
- Ahmed Admin
- QS
- Fathimath QS
- Consultant
- Addu Consult Pvt Ltd
- Start
- —
- Completion
- —