F
Fathimath QS
qs@boq.mv
Settings

Meedhoo Harbour Upgrade

ADM-2026-005 · Ministry of National Planning · Meedhoo

Tender BOQEdit
TypeHarbour/jetty/marine works
LocationMeedhoo, Addu City
ContractLump sum
CurrencyMVR
QSFathimath QS
Completion
Estimated Cost
MVR 5,763,072.00
Subtotal MVR 4,502,400.00
GST
MVR 461,045.76
@ 8% · exclusive
Grand Total
MVR 6,224,117.76
Pending Approvals
0
7 items

Cost by Section

Tap to drill down
VersionTypeItemsStatusUpdated
v1 · Tender BOQ v1Tender BOQ7Tender Issued26/06/2026

Cost Trend (across versions)

v1 Tender BOQ v14,502,400

Cost Build-up

Subtotal
MVR 4,502,400.00
Overhead (10%)
MVR 450,240.00
Profit (10%)
MVR 450,240.00
Contingency (8%)
MVR 360,192.00
Estimated cost
MVR 5,763,072.00
GST @ 8%
MVR 461,045.76
Grand total
MVR 6,224,117.76

Material / Labour / Equipment

Material2,658,600
Labour0
Equipment0
Other1,843,800

Latest BOQ Version

v1 · Tender BOQ v1
Tender Issued

Details

Type
Harbour/jetty/marine works
Contract
Lump sum
Procurement
Open tender
Remoteness
Marine/offshore site
PM
Ahmed Admin
QS
Fathimath QS
Consultant
Addu Consult Pvt Ltd
Start
Completion