F
Fathimath QS
qs@boq.mv
Settings

Meedhoo Friday Mosque Renovation

ADM-2026-004 · Ministry of Islamic Affairs · Meedhoo

Tender BOQEdit
TypeMosque
LocationMeedhoo, Addu City
ContractLump sum
CurrencyMVR
QSFathimath QS
Completion
Estimated Cost
MVR 1,941,625.00
Subtotal MVR 1,553,300.00
GST
MVR 155,330.00
@ 8% · exclusive
Grand Total
MVR 2,096,955.00
Pending Approvals
0
16 items

Cost by Section

Tap to drill down
VersionTypeItemsStatusUpdated
v1 · Tender BOQ v1Tender BOQ16Tender Issued26/06/2026

Cost Trend (across versions)

v1 Tender BOQ v11,553,300

Cost Build-up

Subtotal
MVR 1,553,300.00
Overhead (10%)
MVR 155,330.00
Profit (10%)
MVR 155,330.00
Contingency (5%)
MVR 77,665.00
Estimated cost
MVR 1,941,625.00
GST @ 8%
MVR 155,330.00
Grand total
MVR 2,096,955.00

Material / Labour / Equipment

Material1,333,780
Labour17,920
Equipment0
Other201,600

Latest BOQ Version

v1 · Tender BOQ v1
Tender Issued

Details

Type
Mosque
Contract
Lump sum
Procurement
Open tender
Remoteness
Remote inhabited island
PM
Ahmed Admin
QS
Fathimath QS
Consultant
Addu Consult Pvt Ltd
Start
Completion