Meedhoo Health Centre Extension

ADM-2026-003 · Addu City Council · Meedhoo

Contract BOQEdit
TypeHealth facility
LocationMeedhoo, Addu City
ContractLump sum
CurrencyMVR
QSFathimath QS
Completion26/04/2027
Estimated Cost
MVR 3,448,350.00
Subtotal MVR 2,758,680.00
GST
MVR 275,868.00
@ 8% · exclusive
Grand Total
MVR 3,724,218.00
Pending Approvals
0
20 items

Cost by Section

Tap to drill down
VersionTypeItemsStatusUpdated
v1 · Contract BOQ v1Contract BOQ20Approved26/06/2026

Cost Trend (across versions)

v1 Contract BOQ v12,758,680

Cost Build-up

Subtotal
MVR 2,758,680.00
Overhead (10%)
MVR 275,868.00
Profit (10%)
MVR 275,868.00
Contingency (5%)
MVR 137,934.00
Estimated cost
MVR 3,448,350.00
GST @ 8%
MVR 275,868.00
Grand total
MVR 3,724,218.00

Material / Labour / Equipment

Material1,967,940
Labour23,040
Equipment0
Other767,700

Latest BOQ Version

Details

Type
Health facility
Contract
Lump sum
Procurement
Open tender
Remoteness
Remote inhabited island
PM
Ahmed Admin
QS
Fathimath QS
Consultant
Addu Consult Pvt Ltd
Start
26/04/2026
Completion
26/04/2027