Meedhoo Pre-School (3 Classrooms)
ADM-2026-002 · Ministry of Education · Meedhoo
Construction StageEdit
TypeSchool/classroom
LocationMeedhoo, Addu City
ContractLump sum
CurrencyMVR
QSFathimath QS
Completion26/11/2026
Estimated Cost
MVR 2,298,900.00
Subtotal MVR 1,839,120.00
GST
MVR 183,912.00
@ 8% · exclusive
Grand Total
MVR 2,482,812.00
Pending Approvals
0
20 items
Cost by Section
Tap to drill downBOQ Versions
Open BOQ Editor →| Version | Type | Items | Status | Updated |
|---|---|---|---|---|
| v1 · Construction Stage v1 | Contract BOQ | 20 | Approved | 26/06/2026 |
Cost Trend (across versions)
v1 Construction Stage v11,839,120
Cost Build-up
- Subtotal
- MVR 1,839,120.00
- Overhead (10%)
- MVR 183,912.00
- Profit (10%)
- MVR 183,912.00
- Contingency (5%)
- MVR 91,956.00
- Estimated cost
- MVR 2,298,900.00
- GST @ 8%
- MVR 183,912.00
- Grand total
- MVR 2,482,812.00
Material / Labour / Equipment
Material1,311,960
Labour15,360
Equipment0
Other511,800
Latest BOQ Version
v1 · Construction Stage v1
Approved
Quick Links
Details
- Type
- School/classroom
- Contract
- Lump sum
- Procurement
- Open tender
- Remoteness
- Remote inhabited island
- PM
- Ahmed Admin
- QS
- Fathimath QS
- Consultant
- Addu Consult Pvt Ltd
- Start
- 26/01/2026
- Completion
- 26/11/2026