F
Fathimath QS
qs@boq.mv
Settings

Meedhoo Council Office Building

ADM-2026-001 · Meedhoo Council, Addu City · Meedhoo

Payment CertificationEdit
TypeCouncil/public building
LocationMeedhoo, Addu City
ContractLump sum
CurrencyMVR
QSFathimath QS
Completion26/12/2026
Estimated Cost
MVR 3,831,500.00
Subtotal MVR 3,065,200.00
GST
MVR 306,520.00
@ 8% · exclusive
Grand Total
MVR 4,138,020.00
Pending Approvals
0
20 items

Cost by Section

Tap to drill down
VersionTypeItemsStatusUpdated
v1 · Payment Certification v1Contract BOQ20Approved26/06/2026

Cost Trend (across versions)

v1 Payment Certification v13,065,200

Cost Build-up

Subtotal
MVR 3,065,200.00
Overhead (10%)
MVR 306,520.00
Profit (10%)
MVR 306,520.00
Contingency (5%)
MVR 153,260.00
Estimated cost
MVR 3,831,500.00
GST @ 8%
MVR 306,520.00
Grand total
MVR 4,138,020.00

Material / Labour / Equipment

Material2,186,600
Labour25,600
Equipment0
Other853,000

Latest BOQ Version

Details

Type
Council/public building
Contract
Lump sum
Procurement
Open tender
Remoteness
Remote inhabited island
PM
Ahmed Admin
QS
Fathimath QS
Consultant
Addu Consult Pvt Ltd
Start
26/10/2025
Completion
26/12/2026