Preliminary Estimate v1

Meedhoo Guesthouse (12 Rooms) · v1 · Internal estimate

Draft
20 of 20 items
Item NoDescriptionUnitQuantityRateAmountDrawingSpecStatusRemarksActions
01.00Preliminaries· 3 items
Provisional sum
MVR 165,000.00
📏🧮
Provisional sum
MVR 78,000.00
📏🧮
Provisional sum
MVR 45,000.00
📏🧮
Preliminaries subtotalMVR 288,000.00
03.00Earthworks· 2 items
MVR 25,600.00
📏🧮
MVR 21,600.00
📏🧮
Earthworks subtotalMVR 47,200.00
04.00Concrete Works· 2 items
MVR 114,000.00
📏🧮
MVR 198,250.00
📏🧮
Concrete Works subtotalMVR 312,250.00
05.00Reinforcement· 1 item
MVR 193,200.00
📏🧮
Reinforcement subtotalMVR 193,200.00
06.00Formwork· 1 item
MVR 176,700.00
📏🧮
Formwork subtotalMVR 176,700.00
07.00Masonry and Blockwork· 1 item
MVR 255,500.00
📏🧮
Masonry and Blockwork subtotalMVR 255,500.00
09.00Roofing· 1 item
MVR 194,400.00
📏🧮
Roofing subtotalMVR 194,400.00
10.00Doors and Windows· 2 items
MVR 157,250.00
📏🧮
MVR 75,600.00
📏🧮
Doors and Windows subtotalMVR 232,850.00
13.00Wall Finishes· 1 item
MVR 175,500.00
📏🧮
Wall Finishes subtotalMVR 175,500.00
14.00Floor Finishes· 1 item
MVR 212,500.00
📏🧮
Floor Finishes subtotalMVR 212,500.00
15.00Ceiling Finishes· 1 item
MVR 163,800.00
📏🧮
Ceiling Finishes subtotalMVR 163,800.00
16.00Painting and Decoration· 1 item
MVR 161,500.00
📏🧮
Painting and Decoration subtotalMVR 161,500.00
17.00Plumbing and Sanitary Works· 1 item
Provisional sum
MVR 245,000.00
📏🧮
Plumbing and Sanitary Works subtotalMVR 245,000.00
18.00Electrical Works· 1 item
Provisional sum
MVR 320,000.00
📏🧮
Electrical Works subtotalMVR 320,000.00
21.00External Works· 1 item
MVR 86,800.00
📏🧮
External Works subtotalMVR 86,800.00
SubtotalMVR 3,065,200.00
GST @ 8.0% MVR 245,216.00
Grand TotalMVR 3,310,416.00