Measurement Takeoff
04.001 — Grade C25 reinforced concrete to foundations and ground beams
| Description | Number | Length | Width | Height | Mult. | Deduct. | Formula | Quantity | |
|---|---|---|---|---|---|---|---|---|---|
| 12.000 | |||||||||
| 12.000 | |||||||||
| 12.000 | |||||||||
| 12.000 | |||||||||
| Total quantity | 47.956 m³ | ||||||||
Current BOQ item quantity: 48.000 m³
Takeoff differs by 0.044 m³