F
Fathimath QS
qs@boq.mv
Settings

Rate Analysis

24.002 — Rock armour / geotextile revetment to shoreline protection

← Back to BOQ
ComponentResourceUnitQty/unitUnit costWaste %Amount
907.50
412.50
165.00
165.00
Base rate / 1,485.00

Only Material, Labour, Equipment, Subcontract, Transport and Other lines feed the base rate. Overhead, profit, risk and tax are computed below from project/org percentages.

Rate build-up

per

Direct cost components
Material43%MVR 907.50
Labour20%MVR 412.50
EquipmentMVR 0.00
SubcontractMVR 0.00
Transport8%MVR 165.00
OtherMVR 0.00
Base rateMVR 1,485.00
WastageMVR 45.38
Overhead @ 10.0%MVR 148.50
Profit @ 10.0%MVR 148.50
Risk/contingency @ 8.0%MVR 118.80
Tax @ 8.0%MVR 155.69
Final rateMVR 2,101.86
Current item rate: MVR 1,650.00Δ MVR 451.86