F
Fathimath QS
qs@boq.mv
Settings

Rate Analysis

24.001 — Supply and drive precast concrete piles incl. pile cap

← Back to BOQ
ComponentResourceUnitQty/unitUnit costWaste %Amount
797.50
362.50
145.00
145.00
Base rate / m1,305.00

Only Material, Labour, Equipment, Subcontract, Transport and Other lines feed the base rate. Overhead, profit, risk and tax are computed below from project/org percentages.

Rate build-up

per m

Direct cost components
Material43%MVR 797.50
Labour20%MVR 362.50
EquipmentMVR 0.00
SubcontractMVR 0.00
Transport8%MVR 145.00
OtherMVR 0.00
Base rateMVR 1,305.00
WastageMVR 39.88
Overhead @ 10.0%MVR 130.50
Profit @ 10.0%MVR 130.50
Risk/contingency @ 8.0%MVR 104.40
Tax @ 8.0%MVR 136.82
Final rateMVR 1,847.10
Current item rate: MVR 1,450.00Δ MVR 397.10