Rate Analysis
04.001 — Grade C25 reinforced concrete to foundations and ground beams
| Component | Resource | Unit | Qty/unit | Unit cost | Waste % | Amount | |
|---|---|---|---|---|---|---|---|
| 1,567.50 | |||||||
| 712.50 | |||||||
| 285.00 | |||||||
| 285.00 | |||||||
| Base rate / m³ | 2,565.00 | ||||||
Only Material, Labour, Equipment, Subcontract, Transport and Other lines feed the base rate. Overhead, profit, risk and tax are computed below from project/org percentages.
Rate build-up
per m³
Direct cost components
Material44%MVR 1,567.50
Labour20%MVR 712.50
EquipmentMVR 0.00
SubcontractMVR 0.00
Transport8%MVR 285.00
OtherMVR 0.00
Base rateMVR 2,565.00
WastageMVR 78.38
Overhead @ 10.0%MVR 256.50
Profit @ 10.0%MVR 256.50
Risk/contingency @ 5.0%MVR 128.25
Tax @ 8.0%MVR 262.77
Final rateMVR 3,547.40
Current item rate: MVR 2,850.00Δ MVR 697.40