Maldives Construction & Consulting Pvt Ltd
VARIATION REGISTER

Meedhoo Waste Management Centre

Contractor: Addu Builders Pvt Ltd · Contract Amount: MVR 1,545,372.04

Variations

VO NoDateTypeDescriptionSubmittedAssessedApprovedDaysStatus
VO-0126/05/2025Design change Variation 1: additional foundation works due to soft ground. MVR 15,453.72 MVR 14,681.03 MVR 13,908.35 5 Approved
VO-0226/06/2025Quantity increase Variation 2: increased blockwork to revised layout. MVR 23,180.58 MVR 22,021.55 MVR 20,862.52 10 Recommended
VO-0326/07/2025New item Variation 3: additional external lighting. MVR 30,907.44 MVR 29,362.07 MVR 27,816.70 15 Recommended
Total Approved VariationsMVR 62,587.5730
Revised contract value: MVR 1,607,959.61