Maldives Construction & Consulting Pvt Ltd
VARIATION REGISTER
Meedhoo Waste Management Centre
Contractor: Addu Builders Pvt Ltd · Contract Amount: MVR 1,545,372.04
Variations
| VO No | Date | Type | Description | Submitted | Assessed | Approved | Days | Status |
| VO-01 | 26/05/2025 | Design change |
Variation 1: additional foundation works due to soft ground. |
MVR 15,453.72 |
MVR 14,681.03 |
MVR 13,908.35 |
5 |
Approved |
| VO-02 | 26/06/2025 | Quantity increase |
Variation 2: increased blockwork to revised layout. |
MVR 23,180.58 |
MVR 22,021.55 |
MVR 20,862.52 |
10 |
Recommended |
| VO-03 | 26/07/2025 | New item |
Variation 3: additional external lighting. |
MVR 30,907.44 |
MVR 29,362.07 |
MVR 27,816.70 |
15 |
Recommended |
| Total Approved Variations | MVR 62,587.57 | 30 | |
Revised contract value: MVR 1,607,959.61