Maldives Construction & Consulting Pvt Ltd
PAYMENT CERTIFICATE No. 3

IPC 03

Project: Meedhoo Council Office Building · Contractor: Addu Builders Pvt Ltd
Period: 26/12/2025 – 26/01/2026

Work Done

CodeDescriptionUnitContract QtyCum. QtyRateThis CertCumulative
01.001Mobilization, site establishment and transport of plant & materials to Meedhoosum 1.0000.750 MVR 0.00MVR 0.00 MVR 0.00
01.002Site office, stores, sanitary facilities and temporary services for contract periodsum 1.0000.750 MVR 0.00MVR 0.00 MVR 0.00
01.003Insurances, performance bond and statutory permitssum 1.0000.750 MVR 0.00MVR 0.00 MVR 0.00
03.001Excavate for foundations in all soils incl. disposal of surplus material 80.00060.000 MVR 0.00MVR 0.00 MVR 0.00

Certificate Summary

Gross work doneMVR 2,106,610.20
VariationsMVR 45,502.78
Materials on siteMVR 21,066.10
Gross totalMVR 2,173,179.08
Less retention (5%)MVR -108,658.95
Less previously certifiedMVR -1,434,741.98
Less advance recoveryMVR -140,440.68
Less other deductionsMVR -0.00
NET PAYABLE THIS CERTIFICATEMVR 489,337.47
Quantity Surveyor
Project Manager / Engineer
Employer