| Code | Description | Unit | Contract Qty | Cum. Qty | Rate | This Cert | Cumulative |
|---|---|---|---|---|---|---|---|
| 01.001 | Mobilization, site establishment and transport of plant & materials to Meedhoo | sum | 1.000 | 0.500 | MVR 0.00 | MVR 0.00 | MVR 0.00 |
| 01.002 | Site office, stores, sanitary facilities and temporary services for contract period | sum | 1.000 | 0.500 | MVR 0.00 | MVR 0.00 | MVR 0.00 |
| 01.003 | Insurances, performance bond and statutory permits | sum | 1.000 | 0.500 | MVR 0.00 | MVR 0.00 | MVR 0.00 |
| 03.001 | Excavate for foundations in all soils incl. disposal of surplus material | m³ | 80.000 | 40.000 | MVR 0.00 | MVR 0.00 | MVR 0.00 |
| Gross work done | MVR 1,404,406.80 |
| Variations | MVR 30,335.18 |
| Materials on site | MVR 42,132.20 |
| Gross total | MVR 1,476,874.18 |
| Less retention (5%) | MVR -73,843.71 |
| Less previously certified | MVR -717,370.99 |
| Less advance recovery | MVR -140,440.68 |
| Less other deductions | MVR -0.00 |
| NET PAYABLE THIS CERTIFICATE | MVR 545,218.80 |