Maldives Construction & Consulting Pvt Ltd
PAYMENT CERTIFICATE No. 1

IPC 01

Project: Meedhoo Council Office Building · Contractor: Addu Builders Pvt Ltd
Period: 26/10/2025 – 26/11/2025

Work Done

CodeDescriptionUnitContract QtyCum. QtyRateThis CertCumulative
01.001Mobilization, site establishment and transport of plant & materials to Meedhoosum 1.0000.250 MVR 0.00MVR 0.00 MVR 0.00
01.002Site office, stores, sanitary facilities and temporary services for contract periodsum 1.0000.250 MVR 0.00MVR 0.00 MVR 0.00
01.003Insurances, performance bond and statutory permitssum 1.0000.250 MVR 0.00MVR 0.00 MVR 0.00
03.001Excavate for foundations in all soils incl. disposal of surplus material 80.00020.000 MVR 0.00MVR 0.00 MVR 0.00

Certificate Summary

Gross work doneMVR 702,203.40
VariationsMVR 15,167.59
Materials on siteMVR 63,198.31
Gross totalMVR 780,569.30
Less retention (5%)MVR -39,028.47
Less previously certifiedMVR -0.00
Less advance recoveryMVR -140,440.68
Less other deductionsMVR -0.00
NET PAYABLE THIS CERTIFICATEMVR 601,100.15
Quantity Surveyor
Project Manager / Engineer
Employer