| 01.001 Mobilization, site establishment and transport of plant & materials to Meedhoo | — | MVR 209,979.00 | MVR 226,310.70 | MVR 242,642.40 | MVR 258,974.10 | MVR 275,305.80 |
| 01.002 Site office, stores, sanitary facilities and temporary services for contract period | — | MVR 99,262.80 | MVR 106,983.24 | MVR 114,703.68 | MVR 122,424.12 | MVR 130,144.56 |
| 01.003 Insurances, performance bond and statutory permits | — | MVR 57,267.00 | MVR 61,721.10 | MVR 66,175.20 | MVR 70,629.30 | MVR 75,083.40 |
| 01.004 Marine plant mobilization (barge, crane pontoon, tugs) to site | — | MVR 534,492.00 | MVR 576,063.60 | MVR 617,635.20 | MVR 659,206.80 | MVR 700,778.40 |
| 04.001 Marine-grade reinforced concrete deck slab on piles | — | MVR 3,136.05 | MVR 3,379.97 | MVR 3,623.88 | MVR 3,867.80 | MVR 4,111.71 |
| 24.001 Supply and drive precast concrete piles incl. pile cap | — | MVR 1,239.75 | MVR 1,336.18 | MVR 1,432.60 | MVR 1,529.03 | MVR 1,625.45 |
| 24.002 Rock armour / geotextile revetment to shoreline protection | — | MVR 1,410.75 | MVR 1,520.48 | MVR 1,630.20 | MVR 1,739.93 | MVR 1,849.65 |